Project Overview

The City of Baxter proposes a comprehensive reconstruction of Design Road to address its deteriorated condition, upgrade to 10-ton design standards, and enhance stormwater management. Key improvements include:

Roadway Reconstruction:

  • Replacement of the existing pavement and curb/gutter with a new 6” bituminous layer over a 6” aggregate base.
  • Reduced roadway width to 36’, consistent with local standards for commercial roads.
  • Minor adjustments to pavement markings and signage.
  • Replacement of driveways up to the right-of-way line.

Stormwater System Upgrades:

  • Installation of a new 60” storm sewer pipe to redirect flows to the Whiskey Creek drainage system, bypassing existing constraints under Fleet Farm.
  • Increased system capacity to reduce flooding in adjacent areas and accommodate future connections.

Sanitary Sewer Modifications:

  • Removal and relocation of sewer segments to accommodate the new storm sewer layout.
  • Installation of new cleanouts and adjustments to maintain alignment with modern standards.

Water System Improvements:

  • Exploratory excavation and replacement of plastic watermain tees with ductile iron.
  • Replacement of malfunctioning watermain valves and adjustments to maintain proper separation from sewer lines, with insulation installed where required.

Additional Enhancements:

  • Grade adjustments to minimize surface water ponding.
  • Replacement of pavement markings, signage, driveways, mailbox supports, and water valve box components.

These improvements aim to ensure the long-term functionality of Design Road while addressing safety, drainage, and maintenance needs for the area. If you have questions about the project, please contact Alex Bitter, Project Engineer, at alex.bitter@widseth.com or 218-316-3627.

Construction Updates

8/29/2025

For the remainder of the day, the contractor will be cleaning up the site and should be finishing up switching buildings off temporary water and back on to normal water service. Next week the contractor will be working on installing storm sewer. This will result in a very large excavation down the middle of the roadway. Please continue to use the alternate routes for parking and access. Since the water service work will be completed, the City recommends to have water heaters flushed to make sure they are clean.